Learning objectives
- Load lines feasibly
- Surface delivery risk early
Steps
- Order list with quantities and delivery dates
- Line capacity in SMV per day
- Load styles on lines respecting change-over
- Re-plan weekly with actuals
Factory example
A plan that ignored a 2-day change-over caused a delivery slip — adding change-overs into capacity fixed it.
Common mistakes
- Ignoring change-over
- No weekly re-plan