Production Planning Essentials

guideintermediateLanguage: English

Learning objectives

  • Load lines feasibly
  • Surface delivery risk early

Steps

  1. Order list with quantities and delivery dates
  2. Line capacity in SMV per day
  3. Load styles on lines respecting change-over
  4. Re-plan weekly with actuals

Factory example

A plan that ignored a 2-day change-over caused a delivery slip — adding change-overs into capacity fixed it.

Common mistakes

  • Ignoring change-over
  • No weekly re-plan